Verifications, inspections and review (ITC-BT-05)

Video coming soon

A well-designed installation can be badly built. That is why ITC-BT-05 establishes that, before commissioning, it is verified, and that throughout its life it is inspected periodically in the cases set by the rule. In this lesson you distinguish the initial verification, the initial inspection and periodic inspections, and review the whole week.

Initial verification

It is done by the installer company on completion. It combines a visual examination (cross-sections, colours, protections, labelling) with electrical tests. These include continuity of the protective conductors, insulation resistance (measured with 500 V DC for circuits up to 500 V, with a minimum value of 0.5 MΩ: consult the current ITC), earth electrode resistance and RCD tripping.

text
Ensayos típicos / Typical tests:
  continuidad PE        -> ohmímetro
  aislamiento           -> megóhmetro 500 V DC   (>= 0,5 Mohm, ver ITC vigente)
  toma de tierra        -> telurómetro
  diferencial 30 mA     -> comprobador (dispara <= 300 ms a 30 mA)

Inspections by a control body

Some installations, because of their size or risk, require an initial inspection by a control body (OCA) before commissioning, and all those set by the ITC require periodic inspections. The frequency depends on the type of installation: it is more frequent in public-assembly premises or premises with fire risk than in a dwelling. Consult the current ITC-BT-05 to know which installations and how many years apart.

  • Initial verification: always, done by the installer company.
  • Initial inspection by an OCA: only in the cases laid down.
  • Periodic inspection: depending on installation type.
  • Maintenance: permanent responsibility of the owner.

If an inspection finds defects, they are classified by severity: very serious ones require immediate correction or even disconnecting the supply; serious ones have a deadline for repair. Fixing them is the owner's responsibility, who must hire an installer company and prove the correction.

Week review

Summary of week 2: execution is done by an authorised installer company; documentation is a project or design memorandum plus the registered certificate; safety is checked with the initial verification and the inspections; maintenance belongs to the owner. If you remember that chain, you have the administrative logic of the REBT.

text
Cadena administrativa / Administrative chain:
MTD o proyecto -> ejecución -> verificación -> certificado -> registro -> contrato de suministro
Mantenimiento + inspecciones periódicas = titular

Practical case

A 120 m² bar passes a periodic inspection and the control body finds that the RCD does not trip when the test button is pressed and that several kitchen sockets have no earth connection. The RCD defect is classed as serious and the earth defect as very serious if there is immediate risk. The owner must hire an installer company, repair, provide proof and request a new inspection. With a good monthly maintenance routine, the test button would have revealed the fault months earlier.

Test what you learned

Question 1 of 6

Who builds a low-voltage installation?