Documentation: design memo, project and certificate (ITC-BT-04)
ITC-BT-04 explains which documents are needed to commission an installation. There are three main pieces: the project or design technical memorandum (MTD), the execution with its verifications, and the electrical installation certificate, popularly known as the 'boletín'. Without that registered certificate, the distribution company cannot connect the supply.
Project or design memorandum
Some installations require a project signed by a competent qualified engineer; others only a design memorandum written by the installer company. The decision depends on the type of installation and the power, with thresholds set by ITC-BT-04: consult the current ITC. In a detached house or a flat with the usual power, the design memorandum is typically enough, while a block of flats, a public-assembly venue or a large industrial facility require a project.
Contenido típico de la memoria / Typical memorandum content:
1. datos del titular y emplazamiento
2. potencia prevista y grado de electrificación
3. esquema unifilar (protecciones, secciones, longitudes)
4. cálculos de intensidad y caída de tensión
5. descripción de la puesta a tierraThe installation certificate
On finishing the work and carrying out the verifications, the installer company completes the electrical installation certificate, signs it, hands it to the owner and files it for registration with the competent body of the autonomous community, normally electronically. The certificate records the installation details, the power, the supply type, the test results and a declaration that it complies with the regulation. One copy is for the owner and another for the company.
- Memorandum or project -> execution -> initial verification.
- Certificate signed by the installer company.
- Registration with the autonomous community body.
- Supply contract or change with the distribution company.
- Handing the owner the diagram and the use and maintenance manual.
A common mistake is assuming a small refurbishment needs no paperwork. If the installation is substantially modified (for example, power is increased or new circuits are created), a new certificate may be required. Check the current ITC and your community's procedure before starting.
Datos mínimos de un esquema unifilar / Minimum single-line diagram data:
IGA 25 A -> Dif 40 A / 30 mA -> PIA C1 10 A (1,5 mm2) ... PIA C5 16 A (2,5 mm2)What a good single-line diagram contains
The single-line diagram is the map of the installation. It must show the main switch, the RCD or RCDs, each circuit with its protection and cross-section, the approximate length of the longest circuits and the earthing data. A good diagram lets another professional understand the installation without opening walls, and saves time and mistakes in future extensions. Ideally it is stuck inside the panel door as well as filed with the certificate documents.
✎ My notes
Saved only in this browser. Sign in to keep it in your account.0/5000 characters