Before choosing a cable or a switch you must know how much power the building will need. ITC-BT-10 explains how to calculate the load estimation, which is the maximum power the installation must support. If underestimated, cables overheat and protections trip; if overestimated, the work costs more than necessary. The regulation gives rules to get it right.
Electrification grade of a dwelling
For dwellings there are two grades. Basic electrification covers normal needs and is sized for a minimum of 5750 W at 230 V. Elevated electrification applies when consumption is higher: electric heating, air conditioning, automation, or a large floor area (the regulation sets an area threshold; consult the current ITC) and is sized for at least 9200 W at 230 V. These are minimum design powers, not contracted powers: the user may contract less.
Básica: 5750 W / 230 V = 25 A -> IGA >= 25 A
Elevada: 9200 W / 230 V = 40 A -> IGA >= 40 AResidential buildings
The total load of a building is the sum of the dwellings' loads (with a simultaneity factor that lowers the sum because not everyone consumes at once), of common services (lift, common-area lighting, pumps), of shops and of garages. The simultaneity-factor table is in ITC-BT-10: consult the current ITC. As a guide, for eight dwellings the factor is of the order of 7 rather than 8.
Ejemplo orientativo / Indicative example:
8 viviendas básicas -> 7 x 5750 W = 40 250 W
servicios generales (ascensor, luz comunes) = 6 000 W
total aproximado = 46 250 W -> I = 46250 / (1,732 x 400) = 66,8 AShops and offices are calculated by floor area (of the order of 100 W/m² with a minimum per premises) and garages by area (lower power per square metre, higher if ventilation is forced). The exact values for each premises type must be taken from the current ITC; the important thing here is to understand the method: power per unit, times the number of units, times the simultaneity factor.
Why it matters
All the service-connection cross-sections depend on the load estimation: service line, main protection box, main supply line and individual feeders. A mistake at the start is carried through the whole building. That is why designers spend time on this table before drawing a single cable.
Pregunta clave / Key question:
¿calefacción eléctrica? ¿aire acondicionado? ¿automatización? ¿superficie grande?
alguna = SÍ -> electrificación ELEVADA (9200 W)
todas = NO -> electrificación BÁSICA (5750 W)Practical case: a family buys a 190 m² villa and wants to install a heat pump with electric underfloor heating. Although the appliances would be the usual ones, the electric heating and the large floor area take the dwelling to elevated electrification. In addition, if they later install an electric vehicle charging point, the available power will be key. Thinking about these needs at the start avoids redoing the panel and the individual feeder when everything is already finished.